Saturday, 28 December 2013
New Road Sign of MCC
Monday, 23 December 2013
Will the Campa Cola Judgment Have an Effect in Karnataka?
Monday, 16 December 2013
IT Act non operational in Karnataka
* The Act gives almost unlimited powers to the government to intercept e-mails and thus become a big brother.
* The Act gives validity to e-contracts, but does not define when and where the contract is concluded, unlike similar laws in other countries.
* Drug dealers worldwide are increasingly resorting to the internet. The Act is silent on this issue.
* Since the internet transcends national barriers and many cyber-criminals are outside India, it is not clear if the Act has the jurisdiction to punish them.
* The restrictions on cyber-cafes contained in the Rules made under the Act are so restrictive that if they are really implemented, all cyber-cafes in India would have to be closed.
Saturday, 23 November 2013
The future of power generation in India
1. Rooftop solar photo-voltaic systems which can meet most of the smaller local loads, including domestic needs. Power left after meeting these needs can be exported to the grid.
2. Solar water heaters to provide hot water for houses, nursing homes, hotels, hostels, industries etc. at very economical prices.
3. In places with good average wind speed, wind turbines can provide very cheap power locally.
* a large number of small (rooftop and community-based) power sources,
* some medium/large size renewable power sources (solar, wind, etc.),
* few conventional energy sources,
* higher focus on cutting distribution losses, and
* higher focus on power conservation.
Shankar Sharma
(The author is a power policy analyst and can be contacted at 94482 72503.)
Tuesday, 19 November 2013
Borewells And The Death of Dryland Agriculture
V Mahesha, MGP
(The author, an expert on hydrogeology, worked in the Department of Mines and Geology for more than 35 years in all regions of Karnataka. He can be contacted at 98455 11109.)
Wednesday, 13 November 2013
Campa Cola Judgement and Apartment Owners
The Campa Cola Compound (Worli, Mumbai) case is a classic case of apartment buyers falling prey to the unholy alliance of greedy builders and unethical officials. In 1982, the builders were permitted to construct up to five floors, yet they built several illegal floors on each building, including two towers, without any BMC nod. Having declared the additional floors illegal and ordered for their demolition, in October the Supreme Court granted a four week stay as breathing time to the residents of Campa Cola Society to vacate their illegal flats. The apex court said residents could stay till 11 November only. Instead of complying with the decision of the Supreme Court the residents were attempting to seek the government's help to overcome the problem through an Ordinance and stall the Supreme Court ruling. It is unfortunate that having failed in that attempt the residents are now facing the eviction and demolition of the flats found to be illegal by the Supreme Court.
On 10th November 2013, the Mysore Grahakara Parishat at its monthly meeting had elaborately explained the precautions to be taken by an apartment buyer and had suggested that a copy of the CR, Completion Report issued by the competent authority is a must before a buyer takes possession of his new flat. The Campa Cola case is an example of what could happen if such legal requirements are not complied with. Very soon MGP is coming out with an folder listing Dos and Donts for apartment buyers in Mysore.
The judgement can be read here (pdf).
R Chandraprakash, President, MGP
Sunday, 3 November 2013
Can We Terminate The JUSCO Contract?
In recent days some citizens and politicians have called for termination of the JUSCO contract. Is termination of the JUSCO contract beneficial to our city? We believe that the whole affair is quite messy with no simple answers.
Let us begin at the signing of the contract. The JNNURM-funded project to upgrade Mysore's water supply infrastructure was divided and two tenders were floated for the works. The first one was to build major overhead tanks all over Mysore and supply them with water from the water treatment plants through large underground pipes. Nagarjuna Construction Company won this tender for Rs. 77 crores. The second tender was for doing all the work required to make the present intermittent non-pressurized water supply system into a continuous pressurized 24x7 water supply system and maintaining the system for 6 years. Twelve companies participated in the tender process. JUSCO won the tender with the lowest bid of Rs. 162 crores. Ranhill Water Services made the second lowest bid of Rs. 256 crores, Larsen & Toubro made the third lowest bid at Rs. 305 crores and the highest bid was Rs. 882 crores by Jain Irrigations Systems. So JUSCO's bid was by far the lowest bid.
The JUSCO bid was based on the figures (117,000 connections and 911 km-long pipeline network) given by Mysore City Corporation. Within a year of the beginning of the contract, JUSCO was supposed to carry out a survey, arrive at the actual number of connections and the length of the network and submit a revised estimate based on these figures. According to JUSCO, there were 175,000 connections (an excess of 50% over the MCC figure) and 1911 kms of pipeline (an excess of 110% over the MCC figure). Based on the new numbers, JUSCO submitted a revised estimate of Rs. 212 crores. According to the terms of the contract (Sec. 3.2.7), if the government did not suggest revisions to it within a month, the revised estimate was deemed to have been approved. It appears that the government responded with changes after 3 months and the changes were not acceptable to JUSCO. That is where we stand now. Negotiations are going on between JUSCO and the government in this regard, but nothing concrete has come out. In the meanwhile, JUSCO is finishing up the work covered by the original bid amount and is not taking up any new work. This will leave about half the city without upgradation of the pipeline network and installation of new meters.
In this scenario, let us see what might happen if the JUSCO contract is cancelled. JUSCO will surely approach an arbitrator as provided in the contract (Sec. 24.2). JUSCO might have botched up many things, but the government has also messed up by not rejecting the revised estimate within the specified period and thus becoming liable for the revised estimate of Rs. 212 crores. So the arbitrator may not decide against JUSCO. Even if the decision goes against JUSCO, the remainder of the work has to be tendered again. Based on the original bids, it will be in all likelihood far more costly than the Rs. 50 crores demanded by JUSCO to finish the remaining work. Is the quality of JUSCO work so bad that it is worth paying much more money to another company to finish the work? MCC will have to make this decision. If the quality of JUSCO work is really bad, should the work already done by it be redone by another company? MCC will have to make this decision also.
There are a lot of problems with this project, which should have been anticipated but were not. Some of them are:
1. Splitting the project into two: Nagarjuna Construction Company was given the contract of building the major overhead tanks and JUSCO was given the contract for laying pipes from these tanks to the consumers. If the location of the tanks is not proper, it is not possible to supply water to all consumers at the required pressure. As a result, if water is not being supplied to all consumers at the required pressure, it could be because the design of the pipe network is defective (which would be JUSCO responsibility) or because the location of the tanks is not proper (which would be the responsibility of Nagarjuna). JUSCO and Nagarjuna would blame each other and it would be hard to pin the blame. Such non-accountability should not have been allowed. Tenders should have been called for the combined works and not separately.
2. Making bulk water supply MCC's responsibility and distribution JUSCO's responsibility: The goal of the project is to provide Mysore 24x7 water supply. Dividing the supply responsibility into two again encourages non-accountability. If 24x7 supply is not achieved, JUSCO and MCC will blame each other and it will need an arbitrator to pin the blame.
3. Competence of government: The project was given to private parties because the government felt that its agencies are not competent to do it. If government agencies are not competent to design and execute the works, can they be competent to monitor and control the quality of work done by private agencies? This seems a basic problem with PPP (Private Public Partnership) projects. We have seen in the case of ADB-funded projects a decade ago numerous badly designed and poorly executed works which were approved and passed by the same government agencies as a result of which enormous amounts of money were spent with little lasting value for the city. We routinely see in road repair contracts and irrigation canal repair contracts poor substandard work passed by government agencies. If the competence of government agencies falls below a certain level, even PPPs will not help.
4. Defects in contract: There are numerous defects in the contract. One example is the condition that JUSCO should provide the new water connection to a spot 1 meter inside the customer's property. It is the responsibility of the property owner to lay the pipes from there to the water meter. It is very difficult to get labour for such a small job. Even if labour can be found, the payment demanded is huge. It is amazing that the framers of the contract did not anticipate this problem. They could have fixed the rates for doing this job and given the option of getting the job done by JUSCO or any other contractor to the customer himself. Another example is the common complaint that roads that have been dug up for laying new pipes have not been properly repaired leading to hardship for the locals. Filling the trenches with soil, compacting and resurfacing of the road in a definite time frame could all have been.
V Mahesha, MGP
Monday, 7 October 2013
Petition on Mysore Master Plan
Ashok Kacker, Mysore Grahakara Parishat
Sunday, 6 October 2013
Supreme Court Order on Aadhaar is Being Flouted
Tuesday, 1 October 2013
New team for MGP
Thursday, 12 September 2013
Complaints about bus service
Sunday, 8 September 2013
Courier Service and Law
Is Courier Service Legal?
Courier services are operating in India for decades. But according to Sec. 4 of the Indian Post Office Act, 1898, private parties can not convey letters. Conveying letters is a privilege reserved only for the government. Unsuccessful attempts have been made to update the antiquated law to permit private couriers, but as far as we can tell, Sec. 4 still stands and so strictly speaking, private courier systems are illegal!
M.Akarsh, Mysore Grahakara Parishat
Wednesday, 4 September 2013
Obituary- A R Venkatesan
Tuesday, 27 August 2013
A Clarification from MGP
Wednesday, 21 August 2013
"Maximum Retail Price" Has No Value!
of the Rules prohibits the retail sale of any packaged commodity at a price higher than the printed MRP. So selling above MRP is not prohibited by the Act but is prohibited by the Rules made under the Act.
defeated!
Sunday, 18 August 2013
Traffic Danger
Sunday, 4 August 2013
Why is High-tech Aadhaar Becoming Low-tech?
Tuesday, 30 July 2013
How To Get Your Education Fees Refunded
Monday, 22 July 2013
A Pro-consumer Judgement By The Supreme Court
Monday, 8 July 2013
Is this permitted?
Thursday, 4 July 2013
"Garbage" Photo Contest
Saturday, 22 June 2013
No repairs for FTS building
B.V. Shenoy, Mysore Grahakara Parishat
Thursday, 20 June 2013
Destruction of park in Mysore
The Chief Secretary,
Karnataka State,
Bengaluru
Sir,
1. The Karnataka Parks, Playfields and Open Spaces (preservation and Regulation) Rules, 1985, under which no structure can be constructed within the park if it is less than 2 ha in area and just a watchman’s shed (not exceeding 30 sq.m.) if the area of the park exceeds 2 ha. As against this in this park entire area is dug up, provision is being made to construct shops on one side of the boundary of the park, a high level water tank is being constructed, many sheds for the birds and animals have been built and are being built. In brief the entire park area has been used for the construction of a mini-zoo!!
3. Indian Wildlife Protection Act, 1972 and the The Guidelines of the Central Zoo Authority have been flouted.
We request you to order an enquiry into this entire sordid act. It is surprising as to how such wanton violation of laws have occurred and as to how the officers of the Mysore City Corporation have either overlooked or even connived with such blatant violation.
Yours sincerely,
R Chandra Prakash,
Convener,
Mysore Grahakara Parishat (MGP)
Monday, 17 June 2013
Letter to MLA Vasu
Sri. Vasu,
Hon'ble MLA - Chamaraja Constituency,
Temple Road, Jayalakshmipuram,
Mysore 570 012
Dear Sri Vasu,
Sreemathi Hariprasad,
President,
MGP
Tuesday, 4 June 2013
Be careful about your water storage
Monday, 3 June 2013
Chlorine is dangerous to the RCC of water reservoirs
Saturday, 1 June 2013
Yadavagiri reservoir roof being repaired
Thursday, 30 May 2013
Yadavagiri water reservoir roof collapses again
(Earlier reports on Yadavagiri water reservoir 1, 2, 3)